The Remodeling Master Plan was not only well received but also approved by members present to decide on this proposal at the Extra General Meeting on 23rd February 2006. In the words of the designer , the remodeled Course will bring in its wake more colour and challenges.
The Chairman reassured Members that 18 hole play would be maintained at any one time during the period of Remodeling. The main changes in the Remodeling exercise are as follows:
a. Holes Eliminated - 13,14,15 & 16
Holes Partially affected - 12 & 17
b. New Holes - 1,2,3,4,7,8,9 & 14
Some references between the Remodeled Course and the Existing Course are as follows:-
New Hole 1 will begin at the present Driving Range.
New Holes # 2 & 3 will be along the Tebrau river front.
New Hole 16 is the existing Hole # 7.
c. Existing Holes not mentioned above will also see some changes. Works are expected to commence in mid 2006 and planned for completion within 2 ½ years, if not sooner.
Disruption will be minimal and your understanding is sought to bear with any inconvenience.
|